Key dates
- October 30, 2026Comments on whether EPE's application and notice are sufficientin 7 daysSOAH Order No. 1 (Item 89)
- November 3, 2026Prehearing conference, 10:00 AM CT by Zoom (open to the public)in 11 daysSOAH Order No. 1 (Item 89)
- November 9, 2026Deadline to intervene (become a party)in 17 daysOrder of Referral (Item 88), SOAH Order No. 1 (Item 89)
- April 7, 2027PUC must decide by this datein 166 daysSOAH Order No. 1 (Item 89)
The case
- Applicant
- El Paso Electric Company
- Voltage
- 345 kV
- Estimated cost
- $106–129 million
- Decision due
- April 7, 2027
Where
What you can do
Comment on the record
Anyone can file a public comment. It goes into the official record, but it doesn't make you a party. File through the PUC's Interchange Filer, citing Docket No. 60319.
Intervene by November 9
Landowners and others affected can ask to become a party (intervene). Parties can file testimony, ask questions in discovery, and appear at the hearing, and they must follow the case's deadlines. The judge rules on motions to intervene at the prehearing conference.
Listen in on November 3
The prehearing conference is open to the public by Zoom. The judge will rule on motions to intervene and set the schedule. Connection details are in SOAH Order No. 1 (Item 89).
Timeline
- EPE asks PUC Central Records for a docket number
- EPE files its application with alternative routes
- PUC refers the case to the State Office of Administrative Hearings (SOAH)
- SOAH Order No. 1 sets the intervention deadline and prehearing conference
Latest filings
SOAH · Pleading
SOAH Order No. 1 - Project Description; Jurisdiction, Deadline for Decision, Intervention Deadline; Comments on Sufficiency of Application and Notice; Setting Prehearing Conference; Caution to Interested Parties; and General Procedural Requirements
Item 89 ↗El Paso Electric Company · Pleading
Application of El Paso Electric Company to Amend Its Certificate of Convenience and Necessity for the Pine to McCloud 345 kV Transmission Line in El Paso County - Part 3
Item 85 ↗El Paso Electric Company · Pleading
Application of El Paso Electric Company to Amend Its Certificate of Convenience and Necessity for the Pine to McCloud 345 kV Transmission Line in El Paso County - Part 1
Item 84 ↗El Paso Electric Company · Pleading
Application of El Paso Electric Company to Amend Its Certificate of Convenience and Necessity for the Pine to McCloud 345 kV Transmission Line in El Paso County - Part 2
Item 83 ↗
Questions
What's the difference between commenting and intervening?
A public comment is a statement in the record; you have no further obligations. Intervening makes you a party: you can present evidence and cross-examine witnesses, but you must meet the procedural deadlines, and other parties can send you discovery questions.
Where are the official documents?
Everything is on the PUC's Interchange under Docket 60319. Every filing listed here links to its official copy.